Is there a date for the runways being closed and the Typhoons moving to Kinloss/Leucars? June 2020 was mentioned in one article but wondered if any of the locals knew the latest?
Thanks
Did you know that registration to Fighter Control is completely free and brings you lots of added features? Find out more....
Runway and other Upgrades
Re: Runway and other Upgrades
Update:- This afternoon 05 runway concrete has started to be broken up by JCB Jack hammer.
Re: Runway and other Upgrades
Update:- Ashphalt being planed off on the peritrack from the QRA exit point down towards to Carlie dispersal plus good progress on the breakout of the concrete at the 05 threshold
aye yours Bill R.
aye yours Bill R.
Re: Runway and other Upgrades
Coull962 wrote: ↑Mon Feb 03, 2020 3:21 pmUpdate:- This afternoon 05 runway concrete has started to be broken up by JCB Jack hammer.
They should put pieces of it up for sale like they did with The Berlin Wall back in the day certain if marketed right " Genuine concrete from the main 23/05 runway at RAF lossie a piece of classic Scottish Aviation History , Drakens , Starfighters, Orions, Phantoms , Jaguars , Migs21s, F-111s, Shackletons among others all touched down here" somebody would buy it a paper weight if nothing else
Re: Runway and other Upgrades
Sorry for the spelling mistake in my entry on the 4th should have been CHARLIE dispersal
Cheers Bill R
Cheers Bill R
Re: Runway and other Upgrades
Unfortunately no Drakens, F-104's, F111's or Shackletons landed on the current runway surface, so in this day and age they would end up in court under the trade description act 

Re: Runway and other Upgrades
RAF lossiemouth on Rogue Traders what affront, anyways the memory's are locked in my head LOL
Re: Runway and other Upgrades
23 end of runway, the concrete has been has been broken up, silos have been assembled on a temporary hard core surface made from the graded concrete off of Delta, the large grass area from the VAS Hut on Delta back to the perimeter road (where the traffic light is) has been covered with the skimmed tar from the Northern taxiway. 05 concrete is being crushed and graded for reuse