How to throw away 40 billion in one easy lesson

Post by eagle driver » Tue Oct 17, 2017 7:45 am

108 U.S. F-35s Won’t be Combat-Capable
$21 billion worth of “concurrency orphans”

Dan Grazier
War is Boring

October 16, 2017

The new F-35 program executive officer, U.S. Navy vice admiral Mat Winter, said his office is exploring the option of leaving 108 aircraft in their current state ( http://tinyurl.com/ydbcssns ) because the funds to upgrade them to the fully combat-capable configuration would threaten the Air Force’s plans to ramp up production in the coming years.

These are most likely the same 108 aircraft the Air Force reportedly needed to upgrade earlier in 2017 ( http://tinyurl.com/ycaq3ezs ). Without being retrofitted, these aircraft would become “concurrency orphans” — airplanes left behind in the acquisition cycle after the services purchased them in haste before finishing the development process.

Left unsaid so far is what will become of the 81 F-35s ( http://tinyurl.com/yc8apyl2 ) purchased by the Marine Corps and Navy during that same period. If they are left in their current state, nearly 200 F-35s might permanently remain unready for combat because the Pentagon would rather buy new aircraft than upgrade the ones the American people have already paid for.

What makes this particularly galling is the aircraft that would be left behind by such a scheme were the most expensive F-35s purchased so far. When the tab for all the aircraft purchased in an immature state is added up, the total comes to nearly $40 billion.

That’s a lot of money to spend on training jets and aircraft that will simply be stripped for spare parts.

Empty promises

The Pentagon and Lockheed Martin have been assuring the American people for years that the price tag for the F-35 is on its way down ( http://tinyurl.com/yc3j8gun ). Much of that effort was part of the campaign to convince Congress to approve the Economic Order Quantity ( http://tinyurl.com/yawxknj7 ), or multiple-year block buy of F-35 components.

They claimed that would lead to even more cost savings, but it’s difficult to be enthusiastic about the prospect of saving $2 billion when the program could potentially have wasted up to 10 or perhaps 20 times that amount.

The services will have nearly 800 F-35s either on hand or in the manufacturing pipeline before the design is fully proven through testing under the current plans.

Upgrades are unusually complex for the F-35 because of the design process being used for the program. The program is developing the F-35 in several phases, called blocks. Each block has more capabilities than the earlier version. According to the Lockheed Martin website ( http://tinyurl.com/yag8nvad ), Block 1A/1B combined basic training capabilities with some security enhancements.

Block 2A remained a training version, with the ability to share data between aircraft. Blocks 2B and 3I are the first versions with any combat capabilities. The only significant difference between 2B and 3I is the aircraft’s computer processor.

The first version expected to have full combat capabilities is Block 3F. This version has yet to be completed and is only expected to begin realistic combat testing next year.

The Marine Corps controversially declared Initial Operational Capability with Block 2B aircraft in 2015 ( http://tinyurl.com/pwor2c7 ), but this version is hardly ready for combat ( http://tinyurl.com/hhct64m ). The Pentagon’s testing office has repeatedly said that any pilots flying Block 2B F-35s who find themselves in a combat situation would “need to avoid threat engagement and would require augmentation by other friendly forces” ( http://tinyurl.com/ydc65udx ).

In other words, the 108 Air Force F-35s in question, or any of the Block 2B aircraft, would need to run away from a fight and have other aircraft come to their rescue.

Expensive trainers

Getting to the bottom of exactly how much money has been wasted buying potentially combat-incapable fighters is a bit of a challenge ( http://tinyurl.com/lym4k4o ). There are various ways to calculate the cost of weapon systems. To make it even more difficult, the numbers have been deliberately obscured by the Pentagon and the defense industry over the years ( http://tinyurl.com/y76hfkom ).

Using Lockheed Martin’s own numbers for aircraft deliveries ( http://tinyurl.com/ybu323ak ), it’s possible to make a few calculations to begin to get an idea about how much money may have been spent on these potential concurrency orphans.

The defense industry likes to use the Unit Recurring Flyaway cost. This is just the material cost of the airframe plus the fee to have it put together. This figure sometimes does not include the cost of the engine and it does not include the support and training equipment, spare parts, software upgrades, or contractor fees necessary to actually make the aircraft work.

Under the best case scenario, the only aircraft that would remain concurrency orphans are the 108 Air Force Block 2B and 3I F-35As ( http://tinyurl.com/ycfaa8h7 ). Without knowing exactly when the 108 aircraft in question were built, it’s impossible to know precisely how much was spent to procure them, but using publicly available information, it is possible to calculate a reasonably approximate figure since the Air Force acquired its first 108 F-35As in Low-Rate Initial Production lots one through nine.

Using the Lockheed Martin/Air Force figures ( http://tinyurl.com/y9jmbvd6 ) — which are much lower than the real costs — for the first 108 F-35As purchased, the American people spent approximately $14.117 billion to purchase fighter planes that will never be fully combat-capable unless the Air Force spends the money to upgrade them.

When you factor in the cost of the engine and the support equipment necessary to acquire an aircraft that is actually capable of operating, the dollar amounts are much different than what the Pentagon and Lockheed Martin advertise. This figure can be called the procurement unit cost.

By simply multiplying the number of aircraft purchased per lot by average procurement unit cost for the corresponding year, the American people spent approximately $21.4 billion for those 108 orphaned F-35As ( http://tinyurl.com/yd4hoz7s ). That is slightly more than has been spent on the entire four-year fight against Islamic State ( http://tinyurl.com/yd5unqwe ).

What remains to be seen is what will happen to all of the Block 2B aircraft remaining in the other services. During the period in question, the Marine Corps purchased approximately 53 Block 2B F-35Bs and the Navy purchased 28 Block 2B F-35C variants.

The Project on Government Oversight submitted questions to the F-35 Joint Program Office and Lockheed Martin regarding whether the Navy and Marine Corps aircraft will be upgraded to the fully combat-capable 3F software configuration along with the other concurrency modifications, such as structural reinforcements.

So far, no reply from either office.

When the costs to purchase all variants of the F-35s bought between 2007 and 2014 — the approximate timeframe the first 108 F-35As were purchased — are added together, taxpayers have spent $39.4 billion.
The natural result of concurrency

The risk that the services would be stuck with less than capable aircraft is one that the Pentagon knowingly took when leaders decided to overlap the development and testing of the program with the production. That overlap is what is known as concurrency.

The F-35 program is one of the most concurrent programs in history. The services will have nearly 800 F-35s ( http://tinyurl.com/ybdfeyfa ) either on hand or in the manufacturing pipeline before the design is fully proven through testing under the current plans. This is something former Pentagon acquisition chief Frank Kendall called “acquisition malpractice” ( http://tinyurl.com/7cnk5oh ).

While the F-35 program is still technically in “low-rate initial production,” this is really only true in a strictly legalistic sense. Lockheed Martin is expected to produce ( http://tinyurl.com/yd4rfgu6 ) more than 90 F-35s in 2018.

This, like the 266 previously bought and contracted for — all U.S. F-35s purchased through 2017 — seems to go somewhat beyond the “the minimum needed to provide production representative test articles for operational test and evaluation...to establish an initial production base for the system and provide efficient ramp up to full-rate production” standard established in the Department of Defense acquisition regulations ( https://www.dau.mil/guidebooks/Shared%2 ... 000.02.pdf ).

The danger of purchasing hundreds of aircraft before a program produced a stable and fully tested design has been well known for years. Concurrency, as a RAND Corporation analyst explained in testimony before the House Committee on Government Reform on May 10, 2000, is rooted “in the politics of the acquisition process” ( http://tinyurl.com/y9sck6v5 ).

As POGO has pointed out before ( http://tinyurl.com/ybdzdh6y ), this practice serves to limit the available political options for restructuring programs experiencing significant test failures or cost overruns. When the Pentagon makes substantial procurement commitments well before development or testing is complete, it severely increases the political costs of cancelling the program due to all the money already invested and all the jobs already created.

Dr. Michael Gilmore, the now-retired director of operational test and evaluation, warned that the services would likely have to send aircraft back ( http://tinyurl.com/yckahumx ) to the maintenance depots for modification. The list of modifications is already quite extensive. The Air Force lists 213 change items in its 2018 budget request.

The modifications required go far beyond mere software upgrades. They include serious structural upgrades including fixes to the landing gear, ejection seats, and the aircraft’s bulkhead structures.

Some aircraft would have to undergo this process several times before they could be in full combat configuration.

This is an expensive process. The GAO identified $1.8 billion worth of retrofitting costs to the program in 2016, with $1.4 billion going to already known problems and another $386 million worth of anticipated fixes that had yet to be identified ( http://www.gao.gov/assets/680/676584.pdf ).

These figures are almost certainly much lower than the true cost to retrofit the aircraft already purchased because, as the testing process continues, it’s natural that more and more problems will be revealed. The F-35 program is expected to cost $406.5 billion ( http://tinyurl.com/ycopuv23 ) in development and procurement costs alone.

The true cost to upgrade the earlier generation aircraft must be much higher than what is being publicly reported if the Pentagon has deemed it cheaper to purchase more aircraft.

In total, Congress has authorized — and the Pentagon has spent — nearly $40 billion purchasing approximately 189 F-35s that, in their current configuration, will never be able to perform the way they were expected to when taxpayer dollars were used to buy them. This is hardly the right way to do business.

Any future program must abide by the true spirit of the “fly before you buy” ( http://tinyurl.com/yaehqjur ) business model — unless of course neither Congress nor the Pentagon nor the manufacturers really care about producing an effective and affordable system.

(This story originally appeared at the Project on Government Oversight.)

Reach1985
Posts: 502
Joined: Tue Jul 13, 2010 1:01 pm
Location: Norwich

Re: How to throw away 40 billion in one easy lesson

Post by Reach1985 » Tue Oct 17, 2017 9:42 am

Fascinating - you have to marvel at the waste of money and resource. I can't quite fathom why they are churning out aircraft that can't do the job that they are proposed to do (weapons of war). It looks very much like a PR stunt on the part of the USMC to have the first 'Combat Ready' squadron. Let's hope that they don't get called on to do anything serious this side of 2025!

I recently read the excellent biography of John Boyd https://www.amazon.co.uk/Boyd-Fighter-P ... 0316796883 which recounts his battles during the 1970s with the pentagon and the government to get into production and service the prototypes of what would become the F-15 and F-16 - both of which ended up being compromised in their production versions. Running concurrently you also learn about the gestation of the A-10 and the B-1. The Air Force didn't want the A-10 as it didn't want to do the army co-operation mission what it wanted was the B-1 which with parallels with the F-35 was astronomically expensive and over budget and was in essence a total white elephant (swing-wing was a fairly bad invention - very heavy - Boyd hated the F111 and F-14) so much so that the programme was eventually cancelled however it was then resurrected.

Boyd was very much a fighter man - and was hugely against the 'multi-role' - 'do anything' aircraft - obviously his designs the F-15 and F-16 have become fantastic, combat proven multi-role aircraft - if he was around today who knows what he'd think of that. However reading the book the reader is left in no doubt that if he was stalking the halls of the Pentagon today he'd be fighting tooth and nail to end the F-35 programme.

Supra
Posts: 2721
Joined: Tue Jun 15, 2010 8:01 pm

Re: How to throw away 40 billion in one easy lesson

Post by Supra » Tue Oct 17, 2017 10:23 am

An interesting article on the face of it, complete with sensational title! I must admit the Case for wasted money does seem well founded, but I can't believe this 'concurrency' issue is unique to the F-35 Project. I suspect the real issue here is the unit cost of the F-35 allied to the complexity in 'actually' building-in the upgrades that make it a financial 'non-flyer'!
If one were to study a similar detailed breakdown of the 'Eurofighter/Typhoon' development & production I suspect it wouldn't be so different after applying relative factors?
The burning questions for F-35 detractors like me is.....
1] What exactly have the UK purchased for deployment on the totally not fit for purpose Queen Elizabeth super-targets? That even after 10 years of no shipborne fixed-wing Naval airpower is so much better than we had? ( takes care NOT to say the 'H' word) :whistle:
2] What exactly have the UK purchased for replacing the capable Tornado fleet that makes the overly-fast drawdown of the GR4 still viable? If the Tornado is worn-out, why are we sending them to RTP rather than the smelter? :S

The USA has other assets to prop-up the F-35 in the event of capability shortfall & ongoing product development. The UK don't!

KarlCambs
Posts: 45
Joined: Thu Aug 14, 2014 8:17 pm

Re: How to throw away 40 billion in one easy lesson

Post by KarlCambs » Wed Oct 18, 2017 1:21 pm

The Military Industrial Complex as warned of by Dwight D. Eisenhower in 1961. The arms industry is a massive money making racket with the collusion of national defence forces and arms manufacturers. The Russians spend around 11% of the US defence budget but in relative terms get much more 'bang for their buck' and are able, as in Syria, to deploy and achieve their goals relatively efficiently. $40 billion has lined some some fat cat pockets already with tax payer money, is there any incentive to become more efficient? In a word no. Keep the projects rolling, keep the wars coming, its all to do with profit.

User avatar
Viper28
Posts: 566
Joined: Sun Oct 11, 2009 9:02 pm

Re: How to throw away 40 billion in one easy lesson

Post by Viper28 » Wed Oct 18, 2017 5:45 pm

Although I admit that the numbers are larger, the same is true of the F22A. I might have the exact numbers incorrect but approximately 150 of the fleet have been upgraded to Block-20 and are ''combat coded' and available for deployment. The remaining 30 or so are block-10 and can only be used basically for training.